2014
October - Major equipment procurement complete
May to December - Field preparation continued including plant site grading, auxiliary building construction, utility tie-in, and completing roadway and water supply infrastructure
May - Enhanced PR Spring Project sanctioned by Board of Directors; procurement of major equipment components initiated
April - Received U.S. patent
March - Received independent resources assessment indicating 184.3 million barrels of oil in place
January to December Expanded permanent staff and consulting expertise for project and construction management; invested over 24,000 man-hours of engineering work on the PR Spring Project
2013
November - Ramp-up of all professional and supplier activities for the PR Spring Project
October - Closed $81 million strategic financing that fully funds 2,000 bbl/d PR Spring Project and enables initiation of additional corporate development activities
June - Project work commenced on the PR Spring Project through supply of road-building material and extended duration pump test of the production water well
May to October - Extensive financing related activities including marketing, negotiations, field reviews and due diligence
April - Received independent resources assessment indicating 184.3 million barrels of oil in place
January to December - Progressed final engineering of process designs and continued detailed
2012
August - Received Canadian patent
May to October - Completed field program including drilling 37 core holes, developing a commercial water supply and defining surface miner operation configuration
May - Closed $11.0 million private placement financing to fund 2012 field program, working capital and initial project capital
February - Received independent resource assessment indicating 189.9 million barrels of oil in place
2011
June to November - Completed field program including drilling 180 core holes, evaluating water supply and testing surface mining equipment
June - Closed acquisition of 24,170 acres of undeveloped oil sands leases in the Uinta basin. This new land is referred to as the Cedar Camp Project area
April - Closed $12.6 million private placement financing to fund 2011 field program, lease acquisition and working capital
April - Earth Energy Resources Inc. completed reverse take-over of public company shell, to become US Oil Sands Inc., listed on the TSX Venture Exchange under "USO"
2010
February - Acquired 1,560 acres of land in the Uinta Basin - adding to the PR Spring Project area
January to September - Completed extensive process design work with varying duration runs of the Shop Demonstration Unit
January - Closed $1.1 million private placement financing to fund working capital
2009
September - Received Large Mine Permit approval from the Utah Division of Oil, Gas and Mining
January to December - Completed 16 runs of the Shop Demonstration Unit to gather additional engineering design information
2008
October - Engaged independent process equipment supplier to integrate various solids separation technologies into 2,000 bbl/d commercial extraction process
June - Closed $2.1 million private placement financing
April to December - Completed 27 Shop Demonstration Unit runs to further understand process variables
March - Received Ground Water Discharge Permit-By-Rule approval by Utah Division of Water Quality
February - Acquired 1,905 acres of land in the Uinta Basin - called the Northwest Project area
2007
October - Completed filing of international patent application through World Intellectual Property Organization (WIPO)
September - Submitted Large Mine Application to the Utah Division of Oil, Gas and Mining
July - Engaged independent engineering firm to perform scale-up engineering services and initial process validation
February to December - Completed over 30 Shop Demonstration Unit runs to generate data for scale-up engineering
February - Completed Shop Demonstration Unit in Grande Prairie; commenced testing
2006
September - Conducted electrical resistivity tomography (ERT) on the PR Spring Project area to delineate general bitumen targets and oil sand deposition
April - Acquired 1,808 acres of land in the Uinta Basin - adding to the PR Spring Project area
January - Initiated design and fabrication of 25 bbl/d automated and instrumented Shop Demonstration Unit for testing and collection of commercial engineering information
2005
November - Conducted successful field pilot test in Uinta Basin at PR Spring Project area
October - Closed $5.3 million private placement to fund field pilot test, project capital and working capital
August - Received Small Mine Permit approval by Utah Division of Oil, Gas and Mining
January to June - Acquired 2,562 acres and 50 acres of land in the Uinta Basin - called the PR Spring Project area
2004
October - Began initial international filing of patent
April - Completed 6 hour continuous pilot trial on 25 ton Athabasca oil sand
January to September - Continued development and construction of the extraction process
2003
March to Septemember - Fabricated and developed 150 bbl/d test unit
February - Company incorporated as Earth Energy Resources Inc.